
Albemarle Street, as viewed from 30th Street looking west toward Connecticut Avenue. (December 16th photo)
Now open: Albemarle Street east of Connecticut Avenue, for the first time since a major DC Water closed the section of roadway to vehicle traffic in September 9th, 2024.
Tuesday’s reopening was one of the final and largest steps toward completion of the Soapstone Valley sewer rehabilitation project. Last week, road crews repaved and repainted the street, which had been torn up to replace a manhole. And the work was done a few days ahead of schedule – not typical for a project that was originally projected to last only two months. The overall sewer project – which involved relining and protecting more than 6,000 linear feet of sewer lines in the Soapstone Valley – is ending almost 2 and a half years late.
DC Water says the Albemarle site cleanup should be complete today or tomorrow, and includes removing the construction fencing that was taken down Tuesday and piled in a parking lane.
As for the sewer project, only three more tasks remain: for Pepco to reenergize a streetlight over the manhole site, to replace 19 dead oak saplings that had been planted as part of the Soapstone creek restoration, and to install a fence at the top of a steep stone cascade near the Albemarle trail entrance. ANC 3F requested the addition in 2024 due to safety concerns.
Discover more from Forest Hills Connection | News and Life in Our DC Neighborhood
Subscribe to get the latest posts sent to your email.


Barbara T says
Thanks for this update. So is the Albemarle St trail open yet?
FHC says
Yes, and thanks to you we know that part of the update we wrote did not make it into the published version!
FHC says
The article has been updated to include the trail entrance photo and caption. Thank you again.
HJ says
Thank goodness the work is done, but it was NOT due “early”. The projected completion date was changed many, many, many times, to the point it was done many, many, many months after it was first projected to be done. Even in the past 3-4 months, the projected completion date had been postponed 3 or 4 times. So maybe it was completed “early” compared to the latest completion date, which deserves a “thank you” but not implicit praise for getting the work done early.
Mohammad says
Lets goooo mang. Finally this is open, lets get it poppin….