Preparations are under way for relining a lengthy stretch of century-old sewer pipe along the Soapstone Valley floor. DC Water gave a progress report at ANC 3F’s June 20th meeting […]
Search Results for: soapstone
ANC 3F June 20 agenda: New website, Soapstone sewer progress report, DDOT Stormwater Retrofit Project
ANC 3F’s website at anc3f.com was inaccessible for much of the past month, but they’re working on it. A placeholder page went up recently with information on the commission’s June […]
Soapstone sewer update: July start projected for next relining phase; manholes are holding things up
by Marlene Berlin It’s been only a week since DC Water updated ANC 3F and the community about the timeline for the next phases of the Soapstone sewer project. And […]
The other Soapstone Valley sewer project is a complex operation
by Marlene Berlin Our reporting on DC Water’s Soapstone Valley sewer project has largely focused on the relining of the greater-than-century-old sewer lines. Another, and important, part of the project […]
DC Water’s Soapstone sewer relining work well under way; 2nd stage to begin in May
by Marlene Berlin The relining of the 115-year-old Soapstone Valley sewer has advanced by leaps and bounds since that phase of the sewer rehabilitation project began in mid-March. The pipes […]
ANC 3F March 21 agenda: Soapstone work, stream safety warnings, sidewalk cafes
After DC Water’s March 9th public meeting on the Soapstone Valley sewer rehabilitation project, ANC 3F commissioners still have concerns about the relining process, the noise from water pumps, and […]
March in the Neighborhood: Soapstone sewer project meeting; Make Connecticut Ave. bloom; Welcome spring with dance
Soapstone Park closed one year ago for a project that includes stream restoration, and restoring and protecting the sewer infrastructure in and adjacent to the valley. A new phase is […]
Public Meeting: Soapstone Sewer Rehab Project
DC Water is hosting a virtual public meeting about the Soapstone Valley sewer rehabilitation project on Thursday, March 9th from 7 to 8 p.m. To connect via Microsoft Teams: Click […]
DC Water sets March 13 for Soapstone sewer relining work
Updated below with details of a virtual public meeting on Thursday, March 9th, about the commencement of the relining work. by Mitchell Baer ANC 3F03 commissioner At the February 21st […]
ANC 3F Feb. 21 agenda: Updates on the Soapstone sewer project and a new DC Archives at UDC
At ANC 3F‘s January meeting, DC Water indicated that the relining phase of the Soapstone sewer rehabilitation project would be getting under way by now. The DC Water reps also […]