Forest Hills Connection | News and Life in Our DC Neighborhood

Covering Forest Hills, Van Ness, North Cleveland Park and Wakefield

  • About Us
    • About Forest Hills Connection
    • Contact Us
    • Subscribe to Our Newsletter
    • Donate
    • Advertise
    • Comments Policy
    • Submissions Policy
  • Classifieds
  • News
    • ANC 3F
    • Business
      • Business in Brief
    • Main Street
    • Neighborhood in the News
    • Parks and Streams
    • UDC
  • Style
    • Food
    • History
    • Meet the Neighbors
    • Services
    • Things To Do
  • Home Front
  • Backyard Nature
  • Kids
  • Local Attractions

Search Results for: soapstone sewer

Soapstone sewer updates: UV curing for final pipe segments; Stream restoration plantings begin

February 26, 2024

DC Water’s Soapstone Valley sewer project contractor will be lining the final sewer pipe segments using a method community leaders had urged from the beginning: UV curing. “We have decided to use UV for Lenore Lane, Van Ness [East] and shot 10,” DC Water’s Peter Tinubu, the project manager, told ANC 3F’s February 20th meeting. […]

Filed Under: DC Government, Featured, News, Parks and Streams, Soapstone Valley

ANC 3F February 20 agenda: UDC president, Soapstone sewer work, upcoming special election

February 15, 2024

The February 20th ANC 3F meeting will be the last for James Tandaric as ANC 3F05’s commissioner. Tandaric announced that he is resigning at the end of February. He has been an ANC commissioner since July 2021, and was reelected in November 2022. Tandaric himself joined the commission by filling a mid-term vacancy, and his […]

Filed Under: ANC 3F, DC Government, News, UDC

Soapstone sewer rehab update: May 31 end date and some of the remaining challenges

February 6, 2024

by Marlene Berlin DC Water expects to complete the Soapstone sewer rehabilitation project and reopen the park in four months, though the work remaining includes two Soapstone sewer pipe segments that pose additional challenges. The pipes are along or near steep grades at Lenore Lane and Van Ness East. DC Water, at the January 16th […]

Filed Under: ANC 3F, Featured, Forest Hills, News, Parks and Streams, Soapstone Valley

ANC 3F Jan. 16 agenda: CM Robert White; Soapstone sewer update

January 11, 2024

DC Water’s periodic, opt-in email updates about the Soapstone Valley sewer rehabilitation project can be described as spare. Previous updates might list upcoming activities, like this: Week of January 2, 2024 Perform lateral launch activities on Audubon Terrace And leave it at that. At the last ANC 3F meeting, in November, DC Water was asked […]

Filed Under: ANC 3F, News

Soapstone sewer update: August 21 now tentative date for next relining phase; August 17 virtual meeting

August 7, 2023

On August 21st, DC Water plans to begin installing cured-in-place pipe along a new segment of the 110-year-old sewer pipe in the Soapstone Valley. The agency set out the new, tentative schedule at ANC 3F’s July 18th meeting, and has scheduled a virtual meeting at 7 p.m. on Thursday, August 17th. (See below for the […]

Filed Under: ANC 3F, Featured, News, Parks and Streams, Soapstone Valley

Soapstone sewer update: Preps for next relining phase; noisy stream restoration work on the move; new end date

June 28, 2023

Preparations are under way for relining a lengthy stretch of century-old sewer pipe along the Soapstone Valley floor. DC Water gave a progress report at ANC 3F’s June 20th meeting (video), and set out the next steps ahead of the next round of cured-in-place pipe (CIPP) installation. The first section, marked above by the yellow […]

Filed Under: Featured, News, Parks and Streams, Soapstone Valley

ANC 3F June 20 agenda: New website, Soapstone sewer progress report, DDOT Stormwater Retrofit Project

June 16, 2023

ANC 3F’s website at anc3f.com was inaccessible for much of the past month, but they’re working on it. A placeholder page went up recently with information on the commission’s June 20th virtual meeting, and at the meeting, the commissioners will vote on some expenditures related to getting and keeping a website up and running. Also […]

Filed Under: ANC 3F, News, Soapstone Valley

Soapstone sewer update: July start projected for next relining phase; manholes are holding things up

May 23, 2023

by Marlene Berlin It’s been only a week since DC Water updated ANC 3F and the community about the timeline for the next phases of the Soapstone sewer project. And the schedule has changed already. Last Friday, I was on Audubon Terrace, where DC Water’s Soapstone sewer contractor has pumping equipment for its sewer bypass […]

Filed Under: Featured, News, Soapstone Valley

DC Water’s Soapstone sewer relining work well under way; 2nd stage to begin in May

May 1, 2023

by Marlene Berlin The relining of the 115-year-old Soapstone Valley sewer has advanced by leaps and bounds since that phase of the sewer rehabilitation project began in mid-March. The pipes that carry raw sewage through and around Soapstone Creek, predominantly on National Park Service land, are years beyond their expected life span. They are being […]

Filed Under: Featured, Forest Hills, News, Parks and Streams, Soapstone Valley

March in the Neighborhood: Soapstone sewer project meeting; Make Connecticut Ave. bloom; Welcome spring with dance

March 6, 2023

Soapstone Park closed one year ago for a project that includes stream restoration, and restoring and protecting the sewer infrastructure in and adjacent to the valley. A new phase is getting under way on Monday, March 13th: relining the 115-year-old sewer pipes. In advance of the work, DC Water is hosting a community meeting on […]

Filed Under: News

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • …
  • 17
  • Next Page »

About Forest Hills Connection

  • Who we are
  • How to advertise
  • How to donate
  • How to submit an article
  • Our comments policy
  • Contact us

Connect With Us!

Follow Us on FacebookFollow Us on TwitterFollow Us on Instagram

Latest Comments

  • Barbara Clark on Meet a DC police officer who makes Forest Hills Park one of his daily stops
  • Rebecca Stevens on Meet a DC police officer who makes Forest Hills Park one of his daily stops
  • Tracy on Meet a DC police officer who makes Forest Hills Park one of his daily stops
  • Capt. Tutt on Meet a DC police officer who makes Forest Hills Park one of his daily stops
  • FHC on The long-running Soapstone sewer project is really, truly, actually complete

Archives

About Forest Hills Connection | FHC + VNMS | Who We Are | Contributors
Submissions Policy | Contact | Advertise | Donate |
© Forest Hills Connection | Site by: VanStudios

Loading Comments...